Hubco declares COD for its Chinese joint venture CPHGC

Karachi, August 18, 2019:  China Power Hub Generation Company (CPHGC) – a joint venture between The Hub Power Company Ltd. (HUBCO) and China Power International Holding – has successfully declared the Commercial Operations Date (COD) of its 1320mega watt imported coal power plant and integrated jetty with coal transshipment capacity of 4.2 MTPA.

Developed in record time, as per the schedule and within projected costs, the CPHGC project is a part of the early harvest energy projects under China Pakistan Economic Corridor (CPEC) framework, making it truly a project of national and strategic significance. 

The Plant will add 9 billion kWh of electricity to the national grid every year, meeting the electricity needs of 4 million households in the country.  The Project’s two units achieved synchronization with the National Grid on December 28, 2018, and May 28, 2019, respectively, while the Integrated Coal Jetty became operational in December 2018 with the arrival of the first shipment of coal. 

“The successful completion of CPHGC project has fortified the dream of energy independence of Pakistan. Since the synchronization earlier in May, we conducted extensive testing of the systems to make sure we deliver quality while keeping HSE as our top priority. I am glad that this Pak-China synergy has resulted in engineering excellence and has fulfilled our promise of providing Pakistan with affordable and ample energy” said Mr. Khalid Mansoor, CEO HUBCO.

It is important to note that the Project has also delivered on various social commitments for improving the lives of the local community of Hub and Lasbella.

Together with its partners, CPHGC has set up a school in Gadani, a floating jetty for fishermen in Abbas Village and has conducted various training and development programs for the local youth of Balochistan.  

The Pakistani principal of the project, The Hub Power Company Limited currently produces over 2920 MW through its four plants spread over Baluchistan, Punjab and Azad Jammu & Kashmir.

HUBCO is the only power producer in Pakistan with four projects listed in the CPEC out of which are under- Energy Limited (TEL) and Thalnova Power Thar (Pvt.) Ltd.

Sindh Engro Coal Mining Company (SECMC) at Thar Block II. The power generation capacity of the Company will enhance to over 3580MW after completion of the aforementioned power projects.